 Saturday, November 09, 2019

Crossrail is now running over a million minutes late.

 1 Abbey Wood due 2018   expected 2021 
 2 Abbey Wood due 2018   expected 2021 
 3 Abbey Wood due 2018   expected 2021 
 Services are currently running 1085760 minutes late

An update on progress yesterday confirmed that Crossrail "will open as soon as practically possible in 2021." The railway which was supposed to open last year won't be opening next year after all.

During the early years of the project, its opening date was a distant moveable feast.

2004opening 2012
2006opening 2013
2007opening 2015
2009opening 2017
2011opening 2018

In July 2014 management fixed on December 2018 for the opening of the first section from Paddington and Abbey Wood, with the entire line connected up a year later.

2014opening December 2018

And they stuck to this December 2018 deadline for the next four years, at least in public, with no hints that anything might be awry.

Then in August 2018, one hundred days before the intended opening date, the truth emerged. Problems with signalling and station construction required a delay until "autumn 2019", which of course it now is, so that was an inaccurate prediction too.

This week's announcement is delay number four, like so...

August 2018opening autumn 2019
December 2018opening later than autumn 2019
April 2019opening during the window October 2020 - March 2021
November 2019opening "as soon as practically possible in 2021"

Previously we had a six month window centred on the end of 2020. Now we have a twelve month window centred on the middle of 2021. At the very best that's 1st January 2021, but the direction of travel suggests it'll be a lot later in the year than that.

Crossrail is therefore on track to be at least two, maybe three years late. To put it another way, a railway line which should have opened 11 months ago won't be opening for at least another 14 months, and maybe 25.

The problem is still signalling and stations.

Signalling is difficult when new trains are trying to interface with existing lines and fresh infrastructure. Numerous software versions haven't quite delivered, so have needed significant tweaks, and each period of rewriting slows things down. Version 10 was installed in October, but still doesn't tick all boxes so version 11 is intended to go live next month. If version 11 works then Trial Running will begin "at the earliest possible opportunity in 2020". If it doesn't work then the next stages of testing a fully operational railway will have to be delayed again while we wait for version 12. Let's hope it doesn't take 13.

→  Dynamic
Testing
  →  Trial
Running
  →  Trial
Operations
  →  Passenger
Service
 (we are here)      

As for stations, they're all behind schedule too. It is astonishing that not one of the nine new underground Crossrail stations is yet fully complete, even though they were once supposed to be receiving passengers last year.

Complete by the end of 2019Tottenham Court Road, Farringdon, Custom House
"Substantially complete by the
end of the first quarter in 2020"
Paddington, Liverpool Street, Canary Wharf, Woolwich
Complete heaven knows whenBond Street, Whitechapel

Over the last few months Crossrail have released short progress videos on YouTube for all of these stations.

PaddingtonJul 2019"In the last stages of completion"
Bond StreetJul 2019"Finishing off the bulk of the installs"
Tottenham Court RoadJul 2019"Station build is very nearly complete"
FarringdonOct 2019"Hoarding down", "PPE-free"
Liverpool StreetAug 2019"Testing and commissioning"
WhitechapelJul 2019"Still got a lot to do"
Canary WharfAug 2019"Upgraded all the fire protection"
Custom HouseAug 2019"Scenario testing complete"
WoolwichJul 2019"Substantially complete"

Even once stations are structurally complete, a lengthy programme of safety testing needs to be carried out and this takes many months. Often safety testing can't take place at the same time as test trains are running through the station, and this division of time slows down progress even more.

Bond Street is a real problem because it's so far behind. It needs to be certified safe as an evacuation route before the operational railway can begin, but the testing phase can't begin until construction is complete. Even if every other bit of Crossrail were ready, passenger trains still wouldn't be allowed to operate until Bond Street was available as a potential escape route.

Crossrail is therefore at least One Million Minutes Late, which could stretch to One And A Half Million if the opening date turns out to be at the end of 2021.

We're told that a better estimate of the opening date will be given "early in 2020", once upgraded software finally permits Trial Running to take place. Hopefully they'll confirm that services between Paddington and Abbey Wood will commence in 2021, but I wouldn't bet against the window nudging into 2022.


<< click for Newer posts

click for Older Posts >>


click to return to the main page


...or read more in my monthly archives
Jan19  Feb19  Mar19  Apr19  May19  Jun19  Jul19  Aug19  Sep19  Oct19  Nov19
Jan18  Feb18  Mar18  Apr18  May18  Jun18  Jul18  Aug18  Sep18  Oct18  Nov18  Dec18
Jan17  Feb17  Mar17  Apr17  May17  Jun17  Jul17  Aug17  Sep17  Oct17  Nov17  Dec17
Jan16  Feb16  Mar16  Apr16  May16  Jun16  Jul16  Aug16  Sep16  Oct16  Nov16  Dec16
Jan15  Feb15  Mar15  Apr15  May15  Jun15  Jul15  Aug15  Sep15  Oct15  Nov15  Dec15
Jan14  Feb14  Mar14  Apr14  May14  Jun14  Jul14  Aug14  Sep14  Oct14  Nov14  Dec14
Jan13  Feb13  Mar13  Apr13  May13  Jun13  Jul13  Aug13  Sep13  Oct13  Nov13  Dec13
Jan12  Feb12  Mar12  Apr12  May12  Jun12  Jul12  Aug12  Sep12  Oct12  Nov12  Dec12
Jan11  Feb11  Mar11  Apr11  May11  Jun11  Jul11  Aug11  Sep11  Oct11  Nov11  Dec11
Jan10  Feb10  Mar10  Apr10  May10  Jun10  Jul10  Aug10  Sep10  Oct10  Nov10  Dec10 
Jan09  Feb09  Mar09  Apr09  May09  Jun09  Jul09  Aug09  Sep09  Oct09  Nov09  Dec09
Jan08  Feb08  Mar08  Apr08  May08  Jun08  Jul08  Aug08  Sep08  Oct08  Nov08  Dec08
Jan07  Feb07  Mar07  Apr07  May07  Jun07  Jul07  Aug07  Sep07  Oct07  Nov07  Dec07
Jan06  Feb06  Mar06  Apr06  May06  Jun06  Jul06  Aug06  Sep06  Oct06  Nov06  Dec06
Jan05  Feb05  Mar05  Apr05  May05  Jun05  Jul05  Aug05  Sep05  Oct05  Nov05  Dec05
Jan04  Feb04  Mar04  Apr04  May04  Jun04  Jul04  Aug04  Sep04  Oct04  Nov04  Dec04
Jan03  Feb03  Mar03  Apr03  May03  Jun03  Jul03  Aug03  Sep03  Oct03  Nov03  Dec03
 Jan02  Feb02  Mar02  Apr02  May02  Jun02  Jul02 Aug02  Sep02  Oct02  Nov02  Dec02 