diamond geezer

 Thursday, November 02, 2017

Short version: The Metropolitan Line Extension is doomed because costs have increased and there is no money.

Slightly longer version: Since taking over the MLX project, TfL has worked with the supply chain and Network Rail to progress the design and obtain market prices for delivery. The outturn cost of the project will be significantly in excess of £284.4m. The increased project costs weaken the MLX business case. The deteriorating business case and loss of its operating grant mean that TfL is no longer able to bear cost risk above the current £284.4m funding package.

Long version: Mayoral Decision 2170 Metropolitan Line Extension (MLX) – TfL Funding

Introduction and background

1.1 The MLX project involves the diversion and extension of the existing Metropolitan line from just north of Croxley to a new terminus at Watford Junction. The extension would be routed via two new fully accessible stations, to the existing Watford High Street and Watford Junction Stations. The disused rail corridor would be reinstated and passenger services would cease to operate between Croxley and the existing Metropolitan line terminus, Watford station.

1.2 Initiated in 2011, MLX is a HCC led scheme which at that time had a Department for Transport (DfT) approved funding package of
£116m. HCC were responsible for the overall delivery of the project with TfL being responsible for certain defined elements of scope, such as railway systems. The original funding arrangements envisaged no direct TfL financial contribution.

1.3 In 2013, HCC began reporting a steadily worsening position of cost escalation and programme slippage. In 2014 the DfT considered options to close the MLX funding gap and TfL were identified as the preferred delivery agent for the project. DfT led discussions for the transfer of the project to TfL concluded in March 2015 when TfL was directed by the then Mayor to assume full responsibility for delivering the project.

1.4 MD1478, issued on 26 March 2015, directed TfL to:
a. Take over responsibility for delivering the MLX project.
b. Provide up to £46.5m of funding towards the costs for delivering the MLX based on a total project cost of
£284.4m (the remaining £238m of costs were to be funded from HCC and DfT, as described in 5.1).
c. Be responsible for any overruns above the project estimate of £284.4m.

1.5 MD1570, issued on 4 November 2015, directed TfL to provide up to a further £2.73m of funding, in addition to the £46.5m, towards the cost of delivering the MLX as a substitute for HCC land contributions with an assumed vale of £2.73m, but with no commercial value to TfL.

1.6 On 20 November 2015 the project transferred to TfL with funding arrangements for £284.4m and the two stage main works design and build contract originally let by HCC was novated from HCC to London Underground Limited (Design & Build Contract). At the point of transfer the estimated final cost of the project was
£299m.

1.7 Prior to the project transferring to TfL, the TfL Board noted at its meeting on 1 July 2015 that TfL had not had the opportunity to fully understand the likely cost and delivery requirements associated with the MLX; a project with a known history of cost increases. It was noted that it was then agreed that any cost increases associated with the scheme should be reported back to the DfT.

1.8 Since the transfer of the scheme TfL has undertaken substantial design development and enabling works and completed a thorough review of costs. As work has progressed it has become clear, on the basis of supply chain prices and supplier estimates (including NR), that the outturn cost of the project will be significantly in excess of £284.4m. In June 2017, based on a programme delivery year for completion of 2022, the P50 estimate for delivery of the project was
£333m, with a further £24m of cost pressures identified against this total, which TfL cannot afford to finance. The scope of the project has not changed; the additional cost is a reflection of prices and estimates that TfL has received from the supplier market.

Objectives and expected outcomes

2.1 The key objectives for the MLX are to provide a catalyst for regeneration and growth in the Watford area and improve sustainable connectivity between South West Hertfordshire and North West London. The MLX must meet these objectives by providing a capacity enhancement to support London’s growth and offer the best value for public money.

2.2 At the point of transfer the benefit: cost ratio (BCR) for the MLX (calculated in accordance with webTAG guidance) over a 30 year assessment period was 0.4:1 against a cost of £284.4m. The subsequent cost increases further weaken the BCR.

Other considerations

4.1 The effect of this decision is that
an alternative source of additional funding will need to be identified to cover the costs above the current funding package of £284.4m. These arrangements will need to be in place to allow TfL to commence the necessary procurement and other activities required for TfL to deliver the MLX.

4.2 If the required funding cannot be secured for the scheme to be delivered, reimbursement of sunk project costs is likely to feature in discussions between the funding partners and TfL. The total amount that will have been spent by the time TfL closes-out its activities on the MLX in accordance with this direction (including previous sunk costs prior to the project transferring to TfL) is estimated to be £71.2m. Of this, £32.4m had already been spent prior to the transfer of the scheme to TfL. Of the £38.8m that has been spent post-transfer, £15.5m has been invested in an additional train, which is already in passenger service.

4.3 If no additional funding can be identified in a timely manner, the Transport and Works Act Order (TWAO) powers and planning permission granted in respect of the MLX which are to be implemented by August 2018 may lapse. The expiry of the TWAO powers would result in new powers and planning permissions needing to be sought before any construction activity in respect of the MLX could commence.

Financial comments

5.1 GLA is party to the grant agreement with DfT and is required under the terms of that agreement to transfer the grant to Transport for London. There are otherwise no direct financial implications for the GLA. Below is a breakdown of the funding package for the scheme:

Department for Transport £109.82m
Transport for London (including fare box borrowing) £49.23m
Hertfordshire LEP £87.85m
HCC & Watford Borough Council £37.5m
TOTAL FUNDING £284.40m


5.2 TfL will continue to provide up to £49.23m of funding towards the cost of delivering the MLX subject to TfL not taking responsibility for any costs above the current £284.4m funding package.

5.3 The escalating costs of the MLX (see 1.8) and low forecast passenger numbers have resulted in a deterioration of the business case.
The removal of TfL’s operating grant requires TfL to operate in a sustainable and more efficient manner and ensure that investment in major projects focuses on projects that provide the biggest capacity enhancements to support London’s growth, and offer best value for public money.

5.4 TfL borrowing has to be within the Prudential Code and limits set by the Government. It cannot borrow if its expected income is not sufficient to service its debt.
TfL is close to the maximum level of debt it can afford at present. The cost rise on MLX does not raise additional revenue so borrowing more is not an option.

5.5 These factors mean that TfL is no longer able to bear cost risk above the current £284.4m funding package. TfL could still act as the delivery agent for the MLX if alternative funding arrangements for the project costs above the current £284.4m are made available and subject to the TWAO powers and planning permissions remaining extant.

5.6 TfL will close-out its current activities in respect of the MLX, including the completion of the Stage 1 design, in an orderly fashion and will not commence any new activities, including procurement activities associated with the main works, unless and until arrangements to provide additional funding is put in place.

Legal comments

6.3 The proposed extension is promoted by HCC and is outside Greater London. There is no development directly dependant on the MLX because there are no Grampian planning conditions affecting regeneration and growth in the Watford area linked to the proposed MLX.

Planned delivery approach and next steps

7.1 TfL’s programme for delivering the works will be revised if additional funding for the MLX is committed.

7.2
Unless and until such additional funding for the MLX is committed, TfL will close-out its activities in respect of the project. In particular, the stage 1 design works, being completed through the Design & Build Contract and the Network Rail GRIP3 option selection works will be completed to provide a baseline design for the scheme from which the MLX could be taken forward in the future, subject to the relevant powers and a suitable funding package being made available to secure the delivery of the project.

7.3 Were arrangements to be put in place by DfT and/or local funding partners to provide additional funding for the MLX for costs above the current £284.4m funding package, TfL could consider safeguarding the ability to deliver the scheme beyond the August 2018 deadline. This would involve LUL discharging the pre-commencement planning conditions and exercising compulsory purchase powers (under the TWAO) to enable a discrete package of works to be procured and delivered before that date to demonstrate the scheme had been implemented. However, for TfL to be assured that the programme included a prudent level of contingency to cater for delay (bearing in mind this deadline is absolute),
the additional funding would need to be secured by 31 December 2017.

7.5 Meanwhile the GLA, with support from TfL, will consider whether the project may be suitable for a bid to the Department for Communities and Local Government’s Housing Infrastructure Fund. TfL will also explore with the local funding partners the possibility of developer contributions.


<< click for Newer posts

click for Older Posts >>


click to return to the main page


...or read more in my monthly archives
Jan24  Feb24  Mar24  Apr24  May24  Jun24  Jul24  Aug24  Sep24  Oct24  Nov24
Jan23  Feb23  Mar23  Apr23  May23  Jun23  Jul23  Aug23  Sep23  Oct23  Nov23  Dec23
Jan22  Feb22  Mar22  Apr22  May22  Jun22  Jul22  Aug22  Sep22  Oct22  Nov22  Dec22
Jan21  Feb21  Mar21  Apr21  May21  Jun21  Jul21  Aug21  Sep21  Oct21  Nov21  Dec21
Jan20  Feb20  Mar20  Apr20  May20  Jun20  Jul20  Aug20  Sep20  Oct20  Nov20  Dec20
Jan19  Feb19  Mar19  Apr19  May19  Jun19  Jul19  Aug19  Sep19  Oct19  Nov19  Dec19
Jan18  Feb18  Mar18  Apr18  May18  Jun18  Jul18  Aug18  Sep18  Oct18  Nov18  Dec18
Jan17  Feb17  Mar17  Apr17  May17  Jun17  Jul17  Aug17  Sep17  Oct17  Nov17  Dec17
Jan16  Feb16  Mar16  Apr16  May16  Jun16  Jul16  Aug16  Sep16  Oct16  Nov16  Dec16
Jan15  Feb15  Mar15  Apr15  May15  Jun15  Jul15  Aug15  Sep15  Oct15  Nov15  Dec15
Jan14  Feb14  Mar14  Apr14  May14  Jun14  Jul14  Aug14  Sep14  Oct14  Nov14  Dec14
Jan13  Feb13  Mar13  Apr13  May13  Jun13  Jul13  Aug13  Sep13  Oct13  Nov13  Dec13
Jan12  Feb12  Mar12  Apr12  May12  Jun12  Jul12  Aug12  Sep12  Oct12  Nov12  Dec12
Jan11  Feb11  Mar11  Apr11  May11  Jun11  Jul11  Aug11  Sep11  Oct11  Nov11  Dec11
Jan10  Feb10  Mar10  Apr10  May10  Jun10  Jul10  Aug10  Sep10  Oct10  Nov10  Dec10 
Jan09  Feb09  Mar09  Apr09  May09  Jun09  Jul09  Aug09  Sep09  Oct09  Nov09  Dec09
Jan08  Feb08  Mar08  Apr08  May08  Jun08  Jul08  Aug08  Sep08  Oct08  Nov08  Dec08
Jan07  Feb07  Mar07  Apr07  May07  Jun07  Jul07  Aug07  Sep07  Oct07  Nov07  Dec07
Jan06  Feb06  Mar06  Apr06  May06  Jun06  Jul06  Aug06  Sep06  Oct06  Nov06  Dec06
Jan05  Feb05  Mar05  Apr05  May05  Jun05  Jul05  Aug05  Sep05  Oct05  Nov05  Dec05
Jan04  Feb04  Mar04  Apr04  May04  Jun04  Jul04  Aug04  Sep04  Oct04  Nov04  Dec04
Jan03  Feb03  Mar03  Apr03  May03  Jun03  Jul03  Aug03  Sep03  Oct03  Nov03  Dec03
 Jan02  Feb02  Mar02  Apr02  May02  Jun02  Jul02 Aug02  Sep02  Oct02  Nov02  Dec02 

jack of diamonds
Life viewed from London E3

» email me
» follow me on twitter
» follow the blog on Twitter
» follow the blog on RSS

» my flickr photostream

twenty blogs
our bow
arseblog
ian visits
londonist
broken tv
blue witch
on london
the great wen
edith's streets
spitalfields life
linkmachinego
round the island
wanstead meteo
christopher fowler
the greenwich wire
bus and train user
ruth's coastal walk
round the rails we go
london reconnections
from the murky depths

quick reference features
Things to do in Outer London
Things to do outside London
London's waymarked walks
Inner London toilet map
20 years of blog series
The DG Tour of Britain
London's most...

read the archive
Nov24  Oct24  Sep24
Aug24  Jul24  Jun24  May24
Apr24  Mar24  Feb24  Jan24
Dec23  Nov23  Oct23  Sep23
Aug23  Jul23  Jun23  May23
Apr23  Mar23  Feb23  Jan23
Dec22  Nov22  Oct22  Sep22
Aug22  Jul22  Jun22  May22
Apr22  Mar22  Feb22  Jan22
Dec21  Nov21  Oct21  Sep21
Aug21  Jul21  Jun21  May21
Apr21  Mar21  Feb21  Jan21
Dec20  Nov20  Oct20  Sep20
Aug20  Jul20  Jun20  May20
Apr20  Mar20  Feb20  Jan20
Dec19  Nov19  Oct19  Sep19
Aug19  Jul19  Jun19  May19
Apr19  Mar19  Feb19  Jan19
Dec18  Nov18  Oct18  Sep18
Aug18  Jul18  Jun18  May18
Apr18  Mar18  Feb18  Jan18
Dec17  Nov17  Oct17  Sep17
Aug17  Jul17  Jun17  May17
Apr17  Mar17  Feb17  Jan17
Dec16  Nov16  Oct16  Sep16
Aug16  Jul16  Jun16  May16
Apr16  Mar16  Feb16  Jan16
Dec15  Nov15  Oct15  Sep15
Aug15  Jul15  Jun15  May15
Apr15  Mar15  Feb15  Jan15
Dec14  Nov14  Oct14  Sep14
Aug14  Jul14  Jun14  May14
Apr14  Mar14  Feb14  Jan14
Dec13  Nov13  Oct13  Sep13
Aug13  Jul13  Jun13  May13
Apr13  Mar13  Feb13  Jan13
Dec12  Nov12  Oct12  Sep12
Aug12  Jul12  Jun12  May12
Apr12  Mar12  Feb12  Jan12
Dec11  Nov11  Oct11  Sep11
Aug11  Jul11  Jun11  May11
Apr11  Mar11  Feb11  Jan11
Dec10  Nov10  Oct10  Sep10
Aug10  Jul10  Jun10  May10
Apr10  Mar10  Feb10  Jan10
Dec09  Nov09  Oct09  Sep09
Aug09  Jul09  Jun09  May09
Apr09  Mar09  Feb09  Jan09
Dec08  Nov08  Oct08  Sep08
Aug08  Jul08  Jun08  May08
Apr08  Mar08  Feb08  Jan08
Dec07  Nov07  Oct07  Sep07
Aug07  Jul07  Jun07  May07
Apr07  Mar07  Feb07  Jan07
Dec06  Nov06  Oct06  Sep06
Aug06  Jul06  Jun06  May06
Apr06  Mar06  Feb06  Jan06
Dec05  Nov05  Oct05  Sep05
Aug05  Jul05  Jun05  May05
Apr05  Mar05  Feb05  Jan05
Dec04  Nov04  Oct04  Sep04
Aug04  Jul04  Jun04  May04
Apr04  Mar04  Feb04  Jan04
Dec03  Nov03  Oct03  Sep03
Aug03  Jul03  Jun03  May03
Apr03  Mar03  Feb03  Jan03
Dec02  Nov02  Oct02  Sep02
back to main page

the diamond geezer index
2023 2022
2021 2020 2019 2018 2017
2016 2015 2014 2013 2012
2011 2010 2009 2008 2007
2006 2005 2004 2003 2002

my special London features
a-z of london museums
E3 - local history month
greenwich meridian (N)
greenwich meridian (S)
the real eastenders
london's lost rivers
olympic park 2007
great british roads
oranges & lemons
random boroughs
bow road station
high street 2012
river westbourne
trafalgar square
capital numbers
east london line
lea valley walk
olympics 2005
regent's canal
square routes
silver jubilee
unlost rivers
cube routes
Herbert Dip
metro-land
capital ring
river fleet
piccadilly
bakerloo

ten of my favourite posts
the seven ages of blog
my new Z470xi mobile
five equations of blog
the dome of doom
chemical attraction
quality & risk
london 2102
single life
boredom
april fool

ten sets of lovely photos
my "most interesting" photos
london 2012 olympic zone
harris and the hebrides
betjeman's metro-land
marking the meridian
tracing the river fleet
london's lost rivers
inside the gherkin
seven sisters
iceland

just surfed in?
here's where to find...
diamond geezers
flash mob #1  #2  #3  #4
ben schott's miscellany
london underground
watch with mother
cigarette warnings
digital time delay
wheelie suitcases
war of the worlds
transit of venus
top of the pops
old buckenham
ladybird books
acorn antiques
digital watches
outer hebrides
olympics 2012
school dinners
pet shop boys
west wycombe
bletchley park
george orwell
big breakfast
clapton pond
san francisco
thunderbirds
routemaster
children's tv
east enders
trunk roads
amsterdam
little britain
credit cards
jury service
big brother
jubilee line
number 1s
titan arum
typewriters
doctor who
coronation
comments
blue peter
matchgirls
hurricanes
buzzwords
brookside
monopoly
peter pan
starbucks
feng shui
leap year
manbags
bbc three
vision on
piccadilly
meridian
concorde
wembley
islington
ID cards
bedtime
freeview
beckton
blogads
eclipses
letraset
arsenal
sitcoms
gherkin
calories
everest
muffins
sudoku
camilla
london
ceefax
robbie
becks
dome
BBC2
paris
lotto
118
itv